6.1 Define Activities
Input(3)
Scope baseline
From
5.3 Create WBS
Enterprise environmental factors
Organizational process assets
T&T(4)
Decomposition
Workpackage -> Activities
Rolling wave planning
progressively elaboration
Templates
Activity list
Milestone list
Expert judgment
Expert
Team members
Output(3)
Activity list
To
6.2 Sequence Activities
6.3 Estimate Activity Resources
6.4 Estimate Activity Durations
6.5 Develop schedule
Activity attributes
To
6.2 Sequence Activities
6.3 Estimate Activity Resources
6.4 Estimate Activity Durations
6.5 Develop schedule
Milestrone list
To
6.2 Sequence Activities
6.2 Sequence Activities
Input(5)
Activity list
From
6.1 Define activities
Activity attributes
From
6.1 Define activities
Milestone list
From
6.1 Define activities
Project scope statement
5.2 Define Scope
Organizational process assets
scheduling methodology files
T&T(4)
Precedence diagramming method(PDM)
Dependency determination
Mandatory
Hard logic
Discretionary
Soft logic
External
Applying leads and lags
Schedule network templates
Output(2)
Project schedule network diagrams
Diagrams
AON
not allow dummy activities
precedence diagramming method
AOA
To
6.5 Develop Schedule
Project document updates
Activity lists
Activity attributes
Risk register
6.3 Estimate Activity Resources
Input(5)
Activity list
From
6.1 Define activity
Activity attributes
From
6.1 Define activity
Resource calendars
From
9.2 Acquire Project Team
12.2 Conduct Procurements
Enterprise environmental factors
Organizational process assets
T&T(5)
Expert judgment
Alternatives analysis
Published estimating data
Bottom-up estimating
Project management software
Output(3)
Activity resource requirements
To
9.1 Develop Human Resource Plan
12.1 Plan Procurement
Resource breakdown structure
Project Documents
Project document updates
Activity list
Activity attributes
Resource calendar
6.4 Estimate Activity Durations
Input(7)
Activity list
From
6.1 Define Activities
Activity attributes
From
6.1 Define Activities
Activity resource requirements
From
6.3 Estimate Activity Resources
Resource calendars
From
9.2 Acquire Project Team
12.2 Conduct Procurements
Project scope statement
From
5.2 Define Scope
Enterprise environmental factors
Duration estimating databases
Productivity metrics
Published commercial information
Organizational process assets
Historical duration information
Project calendars
Scheduling methodology
Lessons learned
T&T(5)
Expert judgment
Analogous estimating
Strength
less costly
less time consuming
Weakness
less accurate
Parametric estimating
higher levels of accuracy
Three-point estimates
PERT
Program Evaluation and Review Technique
Most likely
Optimistic
Pessimistic
Expected
O+4M+P / 6
Reserve analysis
time reserves
buffers
Output(2)
Activity duration estimates
To
6.5 Develop Scope
11.2 Identify Risks
Project document updates
Activity attributes
6.1 Define Activities
6.5 Develop Schedule
Input(9)
Activity list
From
6.1 Define Activities
Activity attributes
From
6.1 Define Activities
Project schedule network diagrams
From
6.2 Sequence Activities
Activity resource requirements
From
6.3 Estimate Activity Resources
Resource calendars
From
6.3 Estimate Activity Resources
Activity duration estimates
From
6.4 Estimate Activity Durations
Project scope statement
5.2 Define Scope
Enterprise environmental factors
Organizational process assets
Scheduling methodology
Project calendar
T&T(8)
Schedule network analysis
Critical path method
Critical chain method
Resource leveling
What-if scenario analysis
Monte Carlo Analysis
Applying leads and lags
Schedule compression
Crash
Fast tracking
Scheduling tool
Output(4)
Project schedule
Milestone charts
Bar charts
Project schedule network diagrams
Schedule baseline
Schedule data
Project document updates
Activity resource requirements
6.6 Control Schedule
Input(4)
Project management plan
From
4.2 Develop Project Management Plan
Project schedule
From
6.5 Develop Schedule
Work performance information
From
4.3 Direct and Manage Project Execution
Organizational process assets
T&T(8)
Performance reviews
Variance analysis
Project management software
Resource leveling
What-if scenario analysis
Adjusting leads and lags
Schedule compression
Scheduling tool
Output(5)
Work performance measurements
To
8.3 Perform Quality Control
10.5 Report Performance
Organizational process assets updates
Causes of variances
Corrective action chosen and the reasons
Lessons learned
Change requests
To
4.5 Perform Integrated Change Control
Project management plan updates
Schedule baseline
Schedule management plan
Cost baseline
Project document updates
Schedule data
Project schedule