Phase 1 - 19th March
- Give BSG vlan requirements
- Configure 15 ports on 1BR Basement
-
Move 2 servers to 1 BR
- Not VMs
- Who moves the servers?
- No backup
- No external access
-
Phase 2 - 27th March
- Active Directory on VM
-
Deliver 3 servers
- 2 x Virtual 1 x Physical
- Arm licences for 3 servers
- Shared Storage
-
Phase 3 - 2nd April
- External access to VM
- External access to physical via VM