DEFINE ACTIVITIES
Inputs
Scope Baseline
Enterprise Environmental Factor
Organizational Process Assets
Tools & Techniques
Decomposition
Subdividing the project work packages into smaller more manageable activities
Rolling Wave Planning
progressive elaboration planning where the work to be accomplished in the near term is planned in detail and future work is planned at a higher level
Templates
activity list from a previous project
Expert Judgement
defined by experts
Outputs
Activity List
Activity Attributes
Milestones List
SEQUENCE ACTIVITIES
Inputs
Activity List
Activity Attributes
Milestone List
Project Scope Statement
Organizational Process Assests
Tools & Techniques
Precedence Diagramming Method (PDM)
Finish to Start (FS)
Finish to Finish (FF)
Start to Start (SS)
Start to Finish (SF)
Dependency Determination
Mandatory Dependencies
Discretionary Dependencies
External Dependencies
Applying Leads and Lags
LEAD - ALLOWS AN ACCELERATION OF THE SUCCESSOR ACTIVITY
LAG - DIRECTS A DELAY IN THE SUCCESSOR ACTIVITY
Schedule Network Templates
Outputs
Project Schedule Network Diagrams
Project Document Updates
Activity Lists
Activity Attributes
Risk Register
ESTIMATE ACTIVITY RESOURCES
Inputs
Activity List
Activity Attributes
Resource Calendar
Enterprise Environmental Factors
Organizational Process Assests
Tools and Techniques
Expert Judgement
Alternatives Analysis
Published Estimating Data
Bottom-Up Estimating
Outputs
Activity Resource Requirements
Resource Breakdown Structure
Project Document Updates
Activity Lists
Activity Attributes
Risk Register
ESTIMATE ACTIVITY DURATIONS
Inputs
Activity List
Activity Attributes
Activity Resource Requirements
Resource Calendars
Project Scope Statement
Enterprise Environmental Factors
Organizational Process Assets
Tools and Techniques
Expert Judgement
Analogous Estimating
Parametric Estimating
Three Point Estimates
Most Likely
Optimistic
Pessimistic
Reserve Analysis
Outputs
Activity Duration Estimates
Project Document Updates
DEVELOP SCHEDULE
Inputs
Activity List
Activity Attributes
Project Schedule Network Diagrams
Activity Resource Requirements
Resource Calendar
Activity Duration Estimates
Project Scope Statement
Enterprise Environmental Factors
Organizational Process Assets
Tools & Techniques
Schedule Network Analysis
Critical Path Analysis
Critical Chain Method
Resource Leveling
What-If Scenario
Applying Leads and Lags
Schedule Compression
Crashing
Fast Tracking
Outputs
Project Schedule