1. Work team
    1. CONAFOR ranchers?
      1. Best capacity building for future option
    2. Agustin's contacts (maybe an overlap)
    3. Team of 4 workers required
  2. Existing fenced area (Orchard)
    1. Complete west end irrigation system
      1. New tubes please
        1. Plant infill species
    2. Clear east end ready for planting
      1. Add irrigation system (new tubes please)
        1. Plant out
    3. Draw up the design
    4. Post-rain soil tests (all zones)
    5. Establish M&E indicators for all zones
  3. Nursery
    1. Seed collection
    2. Irrigation system
  4. Silvopastoral/dryland paddock + riparian ribbon
    1. Mark out & seek keyline options (asequia's) for irrigation Q1
      1. Fenced & gated
      2. Develop & install 'monks'
      3. Add in pumped tinaco supply
      4. Begin planting out
    2. Area of action learning
  5. Riparian area below Orchard
    1. Pruned and planned
    2. Fenced & gated
    3. Irrigation system installed
    4. Begin planting out
  6. 25+ Ha zone
    1. Marked out
    2. Fenced & gated
    3. High level cattle trough system installed
    4. Electric fence subdivisions installed
    5. CONAFOR dependent Q4/26 or Q1 2027