Official schedule for submission
- Every year the latest on December
- Revision the lates on July
-
Existing RKAB 2022
-
Approved on 31 January 2022
-
a. Exploration activity
- IDR 14.181.357.750
-
b. Resources & reserves SDE#1
- Resources 414.000,000 ton
- Reserves 118.848.708 ton
-
c. IUP boundaries (21 point)
- Maintenance IDR 130.000.000
- d. Based on existing AMDAL & FS 2014
-
e. Construction
- Explosive bunker
-
f. Mining and processing operations
- Maximum production 167.692 ton
- From development/construction
-
g, Marketing and shipping
- none
-
h. Environment
- Cost management IDR 500.200.000
- Monitoring cost IDR 281.000.000
-
i. Mining safety
- Work safety mining IDR 432.600.000
- Work healthy mining IDR 174.000.000
- Mining environment IDR 136.800.000
- Management system IDR 6.000.000
-
j. Labor & training
- IDR 26.000.000
-
k. CSR
- IDR 130.000.000
-
l. Purchasing
- none
-
m. Finance
- P&L : IDR -673.780.180.100
-
Revision submission (proposal)
-
30 May 2022
-
Construction & infrastructure
(facilities)
- Warehouse
- Workshop
- Employee dormitory
- Industrial park
-
11 June 2022
- Development main tunnel
- Vertical shaft for SDE#2
- Detail of blasting activity
-
30 June 2022
- Minerba request additional data
-
09 Juli 2022
- Minerba request additional data
-
Process
-
Estimation of approval
- 3-4 weeks by system
-
PIC from SDE
-
Technical data
- KTT
-
Follow up
- Ridwan & Fourmarch
- On July, Ridwan request Rachma to follow up to Minerba
-
PIC
- Evaluator
(Yugo)
- Head of Sub-Directorate for Supervision of Coal Production and Marketing Operations
(Ari Katisna)
- Director of Coal Biz. Dev.
(Lana Saria)
- PLH Dirjen Minerba
(Idris Sihite)
- Sekjen ESDM
(Ego Syahrial)
- Minister of Energy and Mineral Resources
(Arifin Tasrif)
-
Issue
- Need to submit new AMDAL & FS
- Prepared by Rachma-Perwita-Amira-Acung
(20-Jul-22)